Tuesday, July 21, 2009

Understanding Power


11th five year plan (FYP) target : 78,000 MW
11th five year plan target : 60,000 MW (Revised)
12th five year plan target : 100,000 MW

Power added in 2008-09 : 12,500 MW
Power targeted to be added in 2010-2012 : 47,500 MW
Power to be added per year in rest of FYP is 15,833 MW

Private Players:
Rosa – Rel Power – 600 MW – End of 2009
Sasan – Rel Power – 1320 MW – End of 2012
Butiburi – Rel Power - 300 MW – End of 2011
Tata Power – 5800 MW – End of 2012
Tata Power / Damodar Valley – 4000 MW – End of 2012
JSW Energy – 1200 MW – Mar 2010
JSW Energy – 2000 MW – ??
Lanco Infratech – 1000 MW – Mar 2010
GVK Power – 1200 MW – End of 2012
Mundra I - Adani Power – 330MW – Jun 2009
Mundra II - Adani Power – 660MW – Feb 2010
Mundra III - Adani Power – 1320MW – Jun 2011
Mundra IV - Adani Power – 1980MW – Apr 2012
Tiroda II - Adani Power – 1980MW – Apr 2012
Indiabulls Power - ?? – End of 2012

Public Players:
NTPC – 30,000MW – End of 2012

No comments: